| Bid Request Number | 2008-011 | ||
| Title | Water Heater Replacement at Bowman Middle School/ Boiler Installation at Rasor Elementary School | ||
| Close Date | 3/26/2008 | Award Info | |
| Line 1 | Turnkey replacement of two (2) natural gas water heaters with expansion tanks at Bowman Middle School | ||
| Name | Price | Note to Buyer | |
| 4-L Engineering Company | $10,800.00 | REPLACE 2 STATE 100 GALLON M/N SBF100199NE WATER HEATERS WITH
STATES SBN100199NE WATER HEATERS. Brand Name: State Model # SBN100199NE |
Awarded Vendor |
| Classic Plumbing, Ltd. | $35,000.00 | PROJECT AT BOWMAN MIDDLE SCHOOL
BID #1 TO REPLACE TWO WATER HEATERS WITH TWO A O SMITH WATER HEATERS TO PLANO ISD SPECTS. BID PULL 2 STATE 100 GAL GAS WH & INST 2 NEW A O SMITH OR EQUAL WH W/EXPANSION TANKS SUPPLIED BY CO Brand: AO Smith Cyclone XHE MOD 400A Model # cyclone XHE MOD 400 A 130 Gal. |
|
| Line 2 | Install District owned boiler and provide and install a 125 gallon storage tank at Rasor Elementary | ||
| Name | Price | Note to Buyer | |
| Classic Plumbing, Ltd. | $6,000.00 | PROJECT AT RASOR ELEMENTARY BID PULL 1 COMMERCIAL WATER HEATER & INSTALL CUSTOMERS BOILER. CONTRACTOR WILL SUPPLY & INSTALL 119 GAL STORAGE WITH EXPANSION TANK THERM-X-TRU L MOD SY-25V OR EQUAL VALUES. | Awarded Vendor |
| 4-L Engineering Company | $9,525.00 | REPLACE 1 PVI 125 GALLON M/N 54V125 BOILER WITH A CUSTOMER FURNISHED LOCHINVAR M/N CEN0500. 4-L WILL FURNISH A LOCHINVAR RJS120, 120 GALLON STORAGE TANK. DOES NOT INCLUDE CONCRETE PAD IF APPLICABLE. 4-L WILL INSTALL THE NEW STORAGE TANK RIGHT OF THE BOILER IN FRONT OF THE 2 CONTROL PANELS. | |