for Parents for Students for Staff
 
Board Agenda : December 12, 2006 : Plano
About Us
Know Your School District
2008-2012
Strategic Plan
Annual Report
Awards & Ratings
Board of Trustees
Leadership Team
Service Departments
Directory of Schools
& Other Facilities
Budget Information
Instructional Program
Policies & Regulations
Purchasing Services
Safety & Security
Advisory Committees
Key Communicators
Education Foundation
Partners & Volunteers
About Plano
Contacts



Board Agenda - December 12, 2006

o. Change order #1 and project close out, Service Center Exterior Wall Repair

Presenter: Richard Matkin

Purpose: A - Request decision - closure required

Time: No time limit

Description:

This Change returns the allowance balances remaining in the project for landscape and irrigation repair and contingency. The landscape and irrigation will be addressed as separate work not under this contract.

The Work of this Contract has been completed, the required closeout documentation is being completed and the Project is ready for Final Acceptance.

Summary:
Original Contract Amount: $ 163,780.00
Previously Approved Change Orders: $ 0.00
Contract Amount prior to this Change Order: $ 163,780.00
This Change Order amount: $ (26,750.00)
Contract Amount after this Change Order: $ 137,030.00

Recommendation:

The Administration recommends that Change Order 1 in the deductive amount of ($26,750.00) be approved. The Architect has reviewed this Change Order and they concur with the amount. The Administration also recommends that the work for the Service Center Wall Repair be accepted, and that final payment, including the release of retainage, be made to Hallman & Keele, Inc.

Business Impact:

Estimated Value: ($26,750.00) Budget/Financial Implication: 2004 Bond Funds