Board Agenda - June 06, 2006
17. Jasper High School gym floor replacement
Presenter: Richard Matkin
Purpose: A - Request decision - closure required
Time: No time limit
Description:
The Gym floors are being replaced at Jasper High School. The current urethane membrane floors will be replaced with wood, similar to the other High School gymnasiums. The floor will be replaced in both gyms at Jasper High School. The District has an approved on-bid vendor with established pricing for this work. The current vendor is Ponder Company, Inc.
Recommendation:
The Administration recommends the approval of the Ponder Company to perform the Jasper High School Gym Floor Replacement.
Business Impact:
Estimated Value: $99,384.00.
Budget/Financial Implication: 2004 Bond Funds, Systems & Compliance.
Summary: